CONSTRUCTION EXECUTION IN NEUSS FOR 2 WIND TURBINES OF THE TYPE E-82 STARTED

Construction phase for 2 wind turbines of the type Enercon E82 is commissioned. Enova acts as a service provider for the Stadtwerke Neuss.

The approval was already given in January 2015. However, the approval was legally fought against by a citizens group. Only in the second instance and one-and-a-half-year duration of proceedings the approval was feasible in the obtained form. Without further delay the execution planning and the appropriate construction execution started.

Current state: access road is constructed. Fundament pit and fundaments are built. Crane assembling for the tower building is planned for KW 40.

Until then the civil engineering measures will be finished. The laying of the cable route will happen parallel to the construction of the wind turbine.

The goal to put into operation with both wind turbines at the end of the year is ensured according to the current planning stage ENOVA is in charge of the surveillance of all construction end the appropriate interface management.