CONSTRUCTION EXECUTION IN NEUSS FOR 2 WIND TURBINES OF THE TYPE E-82 STARTED

Construction phase for 2 wind turbines of the type Enercon E82 is commissioned. Enova acts as a service provider for the Stadtwerke Neuss.

The approval was already given in January 2015. However, the approval was legally fought against by a citizens group. Only in the second instance and one-and-a-half-year duration of proceedings the approval was feasible in the obtained form. Without further delay the execution planning and the appropriate construction execution started.

Current state: access road is constructed. Fundament pit and fundaments are built. Crane assembling for the tower building is planned for KW 40.

Until then the civil engineering measures will be finished. The laying of the cable route will happen parallel to the construction of the wind turbine.

The goal to put into operation with both wind turbines at the end of the year is ensured according to the current planning stage ENOVA is in charge of the surveillance of all construction end the appropriate interface management.

 

E112 Nearshore – ENOVA received order for approval planning.

Within the scope of a service for the nearshore WEA Enercon E112 in Emden, ENOVA was commissioned with the approval planning for the provision of a crane pontoon on the water side and corresponding preparatory measures.

As ENOVA was already in charge of planning the approval as part of the construction of the WEA subject of the application, the available services were used for the approval planning of the upcoming service on the existing know-how of ENOVA.

All the requisite applications and all the necessary authorizations have been duly obtained, despite the tight schedule, thanks to ENOVA’s experience and close contact with the parties involved in the procedure.

Meanwhile, the service intervention on the wind turbine has been successfully realized.

Commisioning Börger Ohe 1

In June of this year, the project Börger Ohe 1 was successfully put into operation. After almost nine months of construction, the ENERCON E115 plant was completed on schedule and on budget.

With a hub height of 149 m and a rotor diameter of 115 m we supply the 3MW wind turbines with an energy amount of approx. 31 GWh/a and cover the annual energy requirement of more than 9000 households. The facilities are located between the towns of Börger and Breddenberg in Emsland.

The first sod was celebrated in Gemünden

The approval phase has been completed – at the end of May, the first ground-breaking ceremony for the seven wind turbines of the new Gemünden wind farm followed. In the coming months, four plants will be built in the city forest of Gemünden and three more in the district of Schiffelbach. The 35 million euro wind farm in the Waldeck Frankenberg district of Hesse is operated by “Windpark Gemünden GmbH”, a subsidiary of VEW.

“We are pleased as a county also with the city of Gemünden and the forest owners, that the construction of the plant can now be started”, said district administrator Dr. med. Reinhard Kubat during the ceremony for the groundbreaking ceremony. He greeted the start of construction together with his mayor Frank Gleim. With the new wind farm, Gemünden can make a contribution towards renewable energies away from fossil fuels. “I’m very proud of that,” says mayor Frank Gleim, who is confident that the city will benefit in the long term.

Each plant will have a height of almost 200 meters with a rotor diameter of 117 meters. The generating capacity of a plant is 2.4 megawatts – so the park has a total output of 16.8 megawatts. The generated energy should be fed into the power grid.

The inauguration of the wind farm is scheduled to take place this fall. On 9 December, the commissioning of the last wind turbine is planned. ENOVA accompanies the project from the beginning. So ENOVA was involved in the determination of the basics, the allocation of wind turbines and the obtaining of the BImSchG.

Ensure strong returns with citizen participation

The energy transition is in full swing. As more and more people want to be part of it, ENOVA now enables citizen participation in the wind farm Börger-Ohe 1.

ENOVA is currently building four wind turbines northeast of the center of Börger in the municipality of Sögel in the state of Sölden. Two of them will be operated by ENOVA in the future and offer interested citizens the opportunity to participate financially in clean energy. The two ENERCON E-115s each have a capacity of 3 MW – in figures this means an output of approx. 15.4 million KWh per year, enough for approx. 4,000 households! And in words: ecological, sustainable power generation, in which every interested party participates.

In the case of investing in the green future, the returns are also worth money if successful: with a yield of 3.75% p.a. – and that from an investment of 500 euros.

Registration for this innovative form of investment is simple and unbureaucratic and works exclusively through the ENOVA website www.buergerbeteiligung.enova.de. Simply register and invest in a proven wind power site in clean and efficient energy production! On the page you will find all the information about the project citizen participation in the wind farm Börger-Ohe 1.

ENOVA new shareholder of GESY

The direct marketing cooperation GESY Green Energy Systems GmbH (GESY) has won three new shareholders, increasing its shareholder base to a total of 16 partners. As a direct marketing partner for renewable energies in Germany, GESY offers a long-term, profitable concept for direct marketing and develops products and business models to master future challenges and exploit the opportunities offered by the energy transition.

The three new GESY shareholders are among the pioneers of the renewable energy sector in project development as well as in the commercial and technical operation of renewable energy plants. With the project developer ENOVA Energiesysteme GmbH & Co. KG from Bunde, a proven onshore and offshore wind specialist has joined the circle of shareholders. Another major project developer and operator of wind turbines, BOREAS Energie GmbH from Dresden has participated in GESY. Psm Nature Power Service & Management GmbH & Co. KG has become a full partner for the commercial and technical operation of renewable energy plants in Erkelenz, NRW.

“Our wide range of marketing experiences across all renewable forms of generation is repeatedly emphasized by our new and existing shareholders as a key competitive advantage in the collaboration,” explains Imber. In addition, the partnership and corporate law sealed exclusive cooperation with the Stadtwerke Trianel cooperation is crucial.

More also under www.gesy.net

It´s going forward in Börger-Ohe!

Stage goal achieved: On 17 December last year, the last of the four foundations of the Börger-Ohe 1 wind farm in Emsland was completed! Good prospects for a smooth further project execution: Also the approval according to BlmSchG was granted in December. The partial permit for the construction of access roads and foundations was already available at this time; Start of the construction was already in November 2015.
In the municipality of Sögel in the state of Sölden four ENERCON E-115 with 3 MW each will be erected, which together generate an output of approx. 34,000,000 kWh per year – enough for approx. 8,500 households! Half of the four wind turbines are operated by landowners and ENOVA; Commissioning is planned for the summer of this year at the latest.

Gemünden wind farm approved: ENOVA as service provider of central partner

In the Hessian Waldeck-Frankenberg district, the starting signal for a new wind farm has been given: in the districts of Schiffelbach and Gemünden (Wohra), seven new wind turbines will be built this year.

ENOVA was commissioned as a service provider for several service phases: from the basic analysis through the approval planning to the participation in the allocation, the wind energy project manager from Bunderhee is involved in the project.

The approval for the € 35 million project was granted in early December 2015. Already before Christmas, the clearing work of the currently used area for forestry began on which in the future the seven Nordex N117 / 2400 with a hub height of 141 m each will stand.

The operator of the wind farm is Windpark Gemünden GmbH, a subsidiary of the association VEW. Commissioning is planned for the first quarter of 2017.

The new highlight in the Rheiderland: ENOVA is repowering a wind energy plant in the industrial area Weener

From now on it is the highest wind energy plant in the Rheiderland: the ENERCON E-101 in the industrial park Weener. After weather-related delays, it was solemnly put into operation by the wind energy project planning team and the client, Klingele Windkraft GmbH. Since 2013, preparations have been made for the repowering of the Nordex N52 wind turbine on the industrial site of Klingele-Papierwerke.


With more power into the new year

135 meters hub height, 101 meters rotor diameter, 3050 kW power – these are the specifications of the E-101, which is in the true sense of the word the new “highlight” of the region. If you look at the performance, the size, however, becomes a minor matter: thanks to repowering, the new wind turbine now produces around 9 million kWh/a, about nine times as much as the old Nordex N54. “The new plant will produce an annual energy yield of around 9 million kW/a,” says Hendrik Stalljann, project manager at ENOVA. “So Klingele is going into the New Year with more power!” Around ten percent of the power demand of the Klingele paper mill could theoretically cover the ENERCON E-101.

 

Leistungen für Industriebetriebe

Operation management for four wind turbines E-126: Wind farm Neuharlingersiel-Werdum.

With the Neuharlingersiel-Werdum project, ENOVA takes over the operational management of a wind farm in the integrated municipality of Esens. Neuh-Werd Energie GmbH & Co. KG commissioned ENOVA in the third quarter of 2015 with the technical operation of the four wind turbines in the district of Wittmund.

The Enercon E-126 systems are currently among the most powerful systems on the market. They have a rated output of approx. 7.6 MW and a rotor diameter of 127 meters. Their hub height is 135 meters. The forecast annual production of the four plants is around 75 million kWh.

»Commissioning: 2014
»Number of systems: 4
»Annual energy production: 75 million kWh